Synthetic Turf Fields

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

SYNTHETIC TURF FIELDS AT SPORTSFIELD PARK

 The Citywide Parks Master Plan identifies the replacement of nearly six acres of grass turf currently utilized as sports fields at the eastern end of Sportsfield Park with all-weather fields constructed from synthetic grass-like material.  The Synthetic Turf Fields will have the capacity to provide two regulation soccer fields but will also allow for the flexible layout of additional fields as needed.               Synthetic Fields    

 

Community Workshops & Meetings

City Council Meeting

Item: Approval of Final Conceptual Master Plan for Synthetic Turf Fields at Sportsfield Park

Date: Thursday, September 13, 2018

Time: 7:30pm

Location: Newark City Hall Council Chambers, 37101 Newark Boulevard – 6th Floor

The City Council will be reviewing the Final Conceptual Master Plan for the Sportsfield Park Synthetic Turf Fields. 

The public is encouraged to attend and provide input on the proposed layout and design of the new sports fields. If you have any questions, please contact Project Manager Jayson Imai at (510) 578-4671 or jayson.imai@newark.org.

Schedule & Updates

A Community Workshop for the new Sportsfield Park Synthetic Turf Fields was held on Tuesday evening, August 14, 2018 at the Silliman Center.  The City’s design consultant, Verde Design, Inc. presented a Preliminary Conceptual Master Plan for the new sports fields.  Residents and representatives from local sports organizations showed their support of the synthetic turf fields and were given the opportunity to express their opinions and provide feedback on the layout included in the Preliminary Conceptual Master Plan.

Turf Fields Prelim Concept Master Plan 08-28-18

Verde Design has taken all of the suggestions and ideas shared at the workshop and used them to develop a Final Conceptual Master Plan for the Sportsfield Park Synthetic Turf Fields, which will be presented to the City Council for review and approval on Thursday evening, September 13, 2018 at 7:30pm at the City Hall Council Chambers. 

If you were unable to attend the City Council meeting but would like to share your ideas for the skate park you can still do so by e-mailing them to the City of Newark at public.works@newark.org

Construction of the Synthetic Turf Fields is anticipated to begin in Spring 2019.

 

Contact Information

Project Manager
Jayson Imai
Assistant City Engineer

jayson.imai@newark.org 

 

Public Works Department
(510) 578-4589
public.works@newark.org